What Is a Piling Mat and What Aggregate Is Used to Build One?

Heavy piling rigs need a firm, stable surface to move across and operate from, particularly where the ground beneath isn’t strong enough to support their concentrated loads on its own. A piling mat provides this temporary working platform, using compacted aggregate to spread the weight of the rig and supporting plant more evenly.

The material and build-up can’t be chosen in isolation, though. They need to suit the ground, equipment and conditions on the individual site. This guide explains what aggregate can be used and how thickness, compaction, drainage and maintenance all contribute to a reliable platform.

What Is a Piling Mat?

A piling mat is a prepared working platform that allows a piling rig to travel between pile positions, set up and operate across the site. It is designed specifically around the loads and movements involved in piling work.

Usually built from compacted granular aggregate, the mat creates a firm, reasonably level surface and helps distribute concentrated rig loads across the subgrade beneath it. This provides more consistent support and reduces the risk of uneven settlement or an isolated soft spot forming beneath one of the tracks.

Depending on the design, the platform may also extend to the ramps and access routes used by the rig and supporting plant.

In this guide, piling mat refers to this granular aggregate platform rather than timber or composite ground-protection mats. It is temporary works for the construction equipment, not part of the building’s permanent piled foundation.

In this guide, piling mat refers to this granular aggregate platform rather than timber or composite ground-protection mats. It is temporary works for the construction equipment, not part of the building’s permanent piled foundation.

Why Do Piling Rigs Need a Designed Platform?

Piling rigs combine considerable weight with a tall structure and concentrated track loads. Even where the surface appears firm, the strength and condition of the ground can vary across the working area. If one section provides less support, the rig could settle unevenly as it moves or operates.

The platform must therefore be designed around the particular rig and its loading arrangements, the condition of the ground, how the equipment will travel between pile positions and any other plant expected to use the area. The aim is to provide consistent support throughout the full working platform, rather than only beneath the rig’s starting position.

What Aggregate Is Used to Build a Piling Mat?

Piling mats are generally built from well-graded granular material that can be compacted into a strong, consistent layer. Depending on the design, this might be crushed quarried rock, clean crushed concrete, approved recycled aggregate or another suitable granular material.

Suitable material needs a grading that allows the particles to interlock, along with enough strength and durability for the expected loading. Its composition and particle size should remain consistent, with timber, metal, organic matter and other unwanted debris properly controlled.

Piling mat aggregate also shouldn’t be confused with open-graded drainage stone. The material needs to compact into a stable working layer, while water is managed through the levels, falls and drainage measures included within the wider platform design.

Is 6F2 Suitable for Piling Mats?

6F2 is commonly used because its mix of particle sizes can form a stable layer when placed and compacted correctly. Armstrongs supplies 6F2 aggregate for piling mats, bulk fill and ground stabilisation.

Its source and composition can vary, so the platform design should confirm the exact material requirements before it is ordered. Our guide to 6F2 and 6F5 explains the wider differences between these classifications.

Can Recycled Aggregate Be Used?

Yes, where the design permits it and the finished aggregate meets the required grading, composition and performance requirements. What matters is the quality and consistency of the supplied product, rather than whether it comes from a quarried or recycled source.

How Thick Should a Piling Mat Be?

There’s no standard thickness suitable for every piling mat. The required depth is calculated from the strength and variability of the subgrade, the rig’s track loading and operating configuration, and the properties of the aggregate being used.

Groundwater, drainage, other plant using the platform and any designed reinforcement can also affect the build-up.

A competent designer should determine the thickness using information for the actual ground and equipment, rather than relying on a general rule of thumb.

Does a Piling Mat Need a Geotextile or Geogrid?

Not necessarily. A geotextile may be used to separate the aggregate from the subgrade and limit the two materials mixing. A geogrid may be included to reinforce or stabilise the granular layer.

They perform different functions, and a piling mat may use either, both or neither depending on its design.

How Is a Piling Mat Constructed?

The exact method varies between sites, but construction should follow the approved temporary-works design from preparation through to completion.

Preparing the Ground

Before aggregate is placed, the formation is prepared to the required level and inspected. Soft or variable areas, former excavations, underground services and other features that could affect support need to be identified and managed.

Any geotextile, geogrid or other specified layer can then be installed in the correct position.

Placing and Compacting the Aggregate

The aggregate is placed in manageable layers and compacted using the plant and method set out for the project. This helps the particles interlock and creates more consistent support through the full depth of the platform.

There’s no universal layer depth or number of passes. Both need to suit the material, compaction equipment and platform design. Our guide to sub-base aggregates explains more about how grading and compaction affect granular layers.

Managing Levels, Edges and Water

The finished surface is trimmed to the required level and kept within the gradients allowed for the rig. Platform edges should be clearly identifiable, while ramps and access routes need to match the planned working area.

Falls, channels or other drainage measures may be used to prevent water collecting on the surface or weakening the ground below. The design may need to account for rainfall, groundwater and water brought to the surface during piling.

How Is a Piling Mat Checked and Maintained?

Completing the platform isn’t the end of its management. Repeated trafficking, wet weather, excavations and changes elsewhere on site can all affect its condition.

What Is a Working Platform Certificate?

The Federation of Piling Specialists’ Working Platform Certificate confirms that the platform has been designed and constructed for the intended plant and will be regularly inspected and maintained. It is signed by the principal contractor and provided to the piling contractor before work begins.

The certificate is an industry control rather than legislation in itself, and it doesn’t replace the responsibilities of those involved in the platform’s design, construction and use. The current FPS Working Platform Guidance provides further information.

What Should Ongoing Checks Cover?

Regular checks may identify rutting, uneven settlement, displaced aggregate, standing water or blocked drainage. Platform edges, ramps and access routes should also be reviewed for damage.

Any excavation, trench or hole made through the platform must be reinstated properly. Tipping loose aggregate into the space may leave an uncompacted soft spot beneath the rig. A change in the plant or working area may also require the design and platform condition to be reviewed.

What Should Be Confirmed Before Ordering Piling Mat Aggregate?

Sharing the relevant project specification before ordering allows the proposed aggregate to be compared with the material requirements

Confirm:

  • The required aggregate designation and grading.
  • Whether quarried, manufactured or recycled material is permitted.
  • Any composition, strength, testing and documentation requirements.
  • The quantity calculated from the designed platform dimensions.
  • The delivery programme, vehicle access and tipping arrangements.
  • How the material will be stored and protected before placement.

An aggregate supplier can provide product information, confirm availability and help plan deliveries. The platform thickness and temporary-works design should remain with the competent project team.

A Reliable Piling Mat Starts With the Right Design and Material

A reliable piling mat brings together suitable ground information, a site-specific design and aggregate that meets the required properties. Careful placement, compaction, drainage and maintenance then help the platform continue providing consistent support throughout the piling work.

Explore Armstrongs’ aggregate range or contact our team with your project specification to discuss material availability and delivery.